Cut & fill volumes
Volumes between the existing surface and design subgrade (finished levels less pavement, slab or topsoil depths), split by area, lot or stage.
Earthworks Estimating
Cut and fill, excavation, backfill and bulk earthworks quantities calculated from your design levels and survey information — with methods and assumptions clearly documented.
How we measure earthworks
Existing and design levels are compared at every point of a survey grid, the topsoil strip is measured, then cut and fill are calculated cell by cell — with bulking and compaction applied to give the site balance.
| Item | Qty | Unit |
|---|---|---|
| Site area 45 × 20 m · 5 m grid | 900 | m² |
| Building platform RL 100.00 subgrade | 700 | m² |
| Topsoil strip 150 mm to stockpile | 135 | m³ |
| Cut to platform bank, incl. batter | 472 | m³ |
| Fill to platform compacted, incl. batter | 283 | m³ |
| Batters trim & topsoil | 169 | m² |
| Cut reused as fill ÷ 0.90 compaction | 314 | m³ |
| Export surplus × 1.25 bulking, loose | 198 | m³ |
| Delivered as an Excel cut/fill report with a marked-up grid plan | ||
Illustrative building platform — sample figures, not a quotation.
Scope
The scope is confirmed with you before work starts, including the calculation method, strip depths and factors, so you know exactly what will be measured and priced.
Volumes between the existing surface and design subgrade (finished levels less pavement, slab or topsoil depths), split by area, lot or stage.
Bulk excavation, including basements, and detailed excavation for footings and pits, with batters and working space where they add volume.
Strip depth over the site area, stockpile volumes and respread to landscaped areas.
Service trenches by depth band, with bedding, pipe surround and backfill measured from the trench details.
Surplus spoil to export and fill to import, after reuse of suitable site-won material.
Bulking and compaction factors, taken from your geotechnical report or instructions and stated as assumptions.
Method
The method depends on the information supplied. It is agreed at scope review and stated in the deliverable, so every volume can be traced back to the surfaces and levels used.
The existing and design surfaces are built as triangulated models from LandXML, CAD or surveyed levels and compared across the site. Best suited to bulk earthworks, building pads and subdivisions.
Cut and fill areas are measured on sections at set chainages and averaged between them (average end area). Suited to roads, channels, embankments and other linear works.
Existing and design levels are compared at each point of a regular grid, and the cut or fill depth is averaged over each cell. Used where only spot levels or a level survey are available.
Deliverables
Cut/fill summary with cut, fill and net volumes by area or stage
Site balance showing reuse, import and export, with bulking and compaction applied
Excavation, trench and backfill schedules in formula-linked Excel
Marked-up PDF plans showing the areas, boundaries and sections measured
Method and assumption notes: surfaces used, strip depths, factors and exclusions
Cost estimate with plant, labour and material breakdown (when pricing is requested)
Ideal for
Dedicated estimator available
Quantifying cut, fill and excavation on a regular basis? Add a dedicated estimator to your team who prepares earthworks quantities and estimates your way, project after project.

How it works
Share drawings, scope and deadline.
We confirm deliverables and timeframe.
Quantities measured and organised.
Checked, then delivered in your format.
Typically an existing surface (survey as LandXML, DWG/DXF or a PDF with spot levels and contours), the design levels or design surface, pavement and slab build-ups, typical sections and, where available, the geotechnical report for strip depths and material reuse. We confirm what is needed once we see the project.
Yes. Volumes are first reported in their in-situ (bank) state. Bulking and compaction factors are then applied as separate lines, so you can see their effect on the site balance and haulage quantities. Factors come from your geotechnical report or instructions and are stated as assumptions.
Yes. Trenches are measured from services layouts, long sections and trench details — excavation by depth band, with bedding, pipe surround and backfill calculated separately.
Standard estimates are typically delivered within 48 hours. Large sites, long road corridors and staged subdivisions take longer. We confirm the delivery date after reviewing your drawings and survey, before work begins.
Related
15Quantities and estimates for earthworks, roads, drainage, utilities and civil concrete.
Learn more
09Accurate measurement and quantification from project drawings.
Learn more
08Concrete quantities, reinforcement and related construction quantities.
Learn moreSend your drawings and scope. We will review the project and confirm deliverables and timing before any work begins.